Meraas24 handed over · 23 in progress · 0 not started · 1 cancelled

At a glance

Updated with deals to 3 Nov 2026
Finishes what it starts21 of 22projects started by 2022

21 finished, 1 cancelled in all.

Due in 20301,676units, on DLD's latest dates

2% built today.

Start to 100%42 monthstypical, of the 24 finished

Half took 38 to 44 months.

Sells off-plan forAED 3,303per sq ft, last 12 months

1-bed homes rent for about 5.0% of the ready price.

Meraas projects, build times and prices

Does Meraas finish what it starts?

21 of 22 projects started by 2022 are finished

Jumeirah Hills - The Palaces was cancelled. 7 of the 22 are registered to Jumeirah Hills Development L.L.C, started in 2015 to 2022. They count here. Many projects started since 2023 are still being built, so those years aren't a result yet. This counts projects, and it says nothing about dates.

Old enough to judge

4
13
4
14
1
15
16
17
1
18
3
19
20
21
9
22

Too recent to judge

8
23
6
24
9
25
3
26
FinishedBeing builtCancelledProjects, by the year they started

What's due, and how built is it?

1,676 units due in 2030

They're 2% built today. Meraas' busiest year so far finished 1,692 units, in 2026.

Most in one year: 1,692
  • Planned end passed
    21244% built
  • 2026
    23864% built
  • 2027
    1,56535% built
  • 2028
    1,10411% built
  • 2029
    7543% built
  • 2030
    1,6762% built
  • No date on record
    1,19326% built
Built so farStill to build

DLD's latest dates, which can move.

Delivery intelligence

Which dates need a closer look?

Active projects past their planned end1 of 19On DLD's latest dates, among projects with a date
Active projects with no planned end41,193 units

How does The Edit At D3 compare with other Meraas projects at the same age?

The Edit At D3Typical Meraas projectMiddle half of Meraas projects

Build intelligence

Is it keeping pace?

It's close to other Meraas projects. It was 0.2% built at 7 months, when they were typically 0.7% built.

  • DLD's latest planned end is Jan 2030.
  • Last inspected on 19 Aug 2026.
  • 313 homes sold in the last 12 months, at about AED 3,306 per sq ft.
See its page →

How far along is what's being built?

Most units are at under 25% built.

Bars show units. Pick a row to list those projects.

How long does Meraas take to build?

Finished projects typically took 42 months from start to 100%. The 9 started in 2022 took longest, about 43 months.

FinishedStill being built, so far

Recent years look quick because only the fastest have finished. Months as DLD records them.

What do Meraas homes sell and rent for?

Most rent for the price1-bed homesA year's rent is about 5.0% of the ready price
Homes sold, last 12 months1,6091,223 off-plan, 386 ready
HomeOff-plan nowRent a yearRent on ready price
1 bedAED 2.59MAED 110k5.0%
2 bedAED 4.37MAED 195k5.0%
3 bedAED 7.72MNot knownNot known
4 bedAED 16.44MNot knownNot known

Sold each month

Oct
Nov
Dec
Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct

Sales were highest in Oct 2025, with 363 registered.

Do Meraas homes resell above their neighbours?

Ready Meraas homes sold for about 23% more than others nearby, per sq ft, across 49 sales in 1 area.

  • Al Wasl
    +23%
MeraasOthers, same home types

Last 12 months. Pale rows have few sales.

Where does Meraas build?

29% of what's being built is in Al Wasl.

  • Al Wasl2,947
  • Um Suqaim Third2,070
  • City Walk1,740
  • Wadi Al Safa 71,199
  • Zaabeel Second837
  • Jumeirah Living832
Finished unitsUnits being built
Meraas logo

Who is behind Meraas?

DLD lists 3 companies as the developer of these projects: Citywalk Residential 1 L.L.C, Dhre 2 Bts L.L.C, Jumeirah Hills Development L.L.C.

Which projects are on Meraas' record?

ProjectAreaUnitsBuiltStartedMilestoneSold, 12 monthsPer sq ftCheck
Bulgari Lighthouse DubaiIsland 23180%Feb 2023Planned Mar 20271None yet
ElaraUm Suqaim Third23864%Nov 2023Planned Nov 20268AED 2,712
Central Park PlazaAl Wasl21244%Dec 2023Planned Oct 20261None yet
Design QuarterDubai Design District56441%May 2023Planned Feb 202720AED 2,568
City Walk Northline 1Al Wasl11538%Aug 2024No date on record5AED 2,716
City Walk Northline 2Al Wasl19237%Aug 2024No date on record10AED 2,683
Bluewaters BayMarsa Dubai67937%Feb 2023Planned Mar 202736AED 3,739
The AcresWadi Al Safa 764225%Sep 2024No date on record56Sold as land

Questions people ask

Quick answers, from the same deals as the rest of this page.

How many projects has Meraas finished?

24, with 5,015 units.

How long does Meraas take to build?

About 42 months from start to 100%, for the 24 that have finished.

Does Meraas finish on time?

DLD's dates can't tell you, because DLD often replaces the planned date with the finish date once a project is done. Of projects started by 2022, 21 of 22 are finished.

Has Meraas cancelled any projects?

1, on DLD's record: Jumeirah Hills - The Palaces.

Which company is behind Meraas?

DLD lists Citywalk Residential 1 L.L.C as the developer.

About our data

Where our numbers come from

Project status comes from DLD's project records, read on 5 Nov 2026. Prices come from every sale registered with DLD, to 3 Nov 2026.

What's counted
Projects DLD lists under Citywalk Residential 1 L.L.C, plus 11 projects under Dhre 2 Bts L.L.C and 11 projects under Jumeirah Hills Development L.L.C.
Finishes what it starts
Projects by start year and their DLD status today. A start year counts as old enough once the typical build time has passed. It says nothing about whether dates were met.
Units
DLD's count for each project. It can include shops and offices as well as homes.
Build time
Months from DLD's start date to the first inspection at 100%, for projects that have finished. Projects still running aren't in it.
Typical at the same age
How built the developer's other projects were at the same number of months, finished and still running, using the middle project.
Planned end
DLD's latest date. DLD can rewrite it, and often replaces it with the finish date once a project is done, so we never use it to say a developer finished on time.
Neighbours
Ready sales in the last 12 months in the same area, from other developers. Home types are weighted to match, so a studio-heavy developer isn't compared with family homes.
Rent on ready price
A year of new-lease rent on this developer's buildings, as a share of the typical ready price, before service charges and fees.

We update with every data release. This page was last updated on 3 Nov 2026.

Free · From deals registered with the DLD

What are you looking at?

Try