Emaar logo

Emaar175 handed over · 120 in progress · 17 not started · 14 cancelled

At a glance

Updated with deals to 3 Nov 2026
Finishes what it starts156 of 170projects started by 2022

156 finished, 3 still being built, 14 cancelled in all.

Due in 202917,084units, on DLD's latest dates

12% built today.

Start to 100%44 monthstypical, of the 136 finished

Half took 35 to 58 months.

Sells off-plan forAED 2,275per sq ft, last 12 months

3-bed homes rent for about 6.2% of the ready price.

Emaar projects, build times and prices

Does Emaar finish what it starts?

156 of 170 projects started by 2022 are finished

The St. Regis Residences, Downtown Dubai is still being built, 116 months in and 76% built. Address The Bay is still being built, 48 months in and 70% built. Marina Shores is still being built, 47 months in and 87% built. 11 were cancelled. 117 of the 170 are registered to 6 other companies. They count here. Many projects started since 2023 are still being built, so those years aren't a result yet. This counts projects, and it says nothing about dates.

Old enough to judge

1
98
99
4
00
8
01
6
02
03
3
04
05
5
06
5
07
5
08
1
09
10
11
7
12
8
13
13
14
10
15
9
16
22
17
8
18
27
19
8
20
5
21
15
22

Too recent to judge

29
23
41
24
50
25
36
26
FinishedBeing builtCancelledProjects, by the year they started

What's due, and how built is it?

17,084 units due in 2029

They're 12% built today. Emaar's busiest year so far finished 7,743 units, in 2023.

Most in one year: 7,743
  • Planned end passed
    15531% built
  • 2026
    2,57179% built
  • 2027
    92581% built
  • 2028
    11,72532% built
  • 2029
    17,08412% built
  • 2030
    6,7920.4% built
  • 2031
    1,5550% built
  • No date on record
    5,19761% built
Built so farStill to build

DLD's latest dates, which can move.

Delivery intelligence

Which dates need a closer look?

Active projects past their planned end1 of 118On DLD's latest dates, among projects with a date
Active projects with no planned end195,197 units

How does Creek Bay compare with other Emaar projects at the same age?

Creek BayTypical Emaar projectMiddle half of Emaar projects

Build intelligence

Is it keeping pace?

It's close to other Emaar projects. It was 0.6% built at 3 months, when they were typically 0.9% built.

  • DLD's latest planned end is Apr 2030.
  • Last inspected on 16 Jun 2026.
  • 702 homes sold in the last 12 months, at about AED 2,736 per sq ft.
See its page →

How far along is what's being built?

1 had no building work at their last inspection, taken around when they started. They started 18 to 18 months ago.

Bars show units. Pick a row to list those projects.

How long does Emaar take to build?

Finished projects typically took 44 months from start to 100%. The 8 started in 2013 took longest, about 70 months.

FinishedStill being built, so far

Recent years look quick because only the fastest have finished. Months as DLD records them.

What do Emaar homes sell and rent for?

Most rent for the price3-bed homesA year's rent is about 6.2% of the ready price
Sold as landAED 8.36MTypical, 2,332 sales. DLD gives no home type
HomeOff-plan nowRent a yearRent on ready price
StudioNone yetAED 76k5.0%
1 bedAED 1.84MAED 100k5.3%
2 bedAED 2.92MAED 150k4.9%
3 bedAED 3.64MAED 240k6.2%
4 bedAED 4.64MNot knownNot known

Sold each month

Oct
Nov
Dec
Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct

Sales were highest in Jan 2026, with 2,259 registered.

Do Emaar homes resell above their neighbours?

Ready Emaar homes sold for about 33% more than others nearby, per sq ft, across 1,347 sales in 3 areas.

  • Burj Khalifa
    +44%
  • Dubai Hills
    -2%
  • Dubai Marina
    +7%
  • Madinat Al Mataar
    +15%
EmaarOthers, same home types

Last 12 months. Pale rows have few sales.

Where does Emaar build?

14% of what's being built is in Madinat Al Mataar.

  • Burj Khalifa17,034
  • Dubai Creek Harbour14,556
  • Al Yufrah 18,078
  • Madinat Al Mataar6,801
  • Al Khairan First5,778
  • Dubai Harbour5,699
Finished unitsUnits being built
Emaar logo

Who is behind Emaar?

DLD lists 8 companies as the developer of these projects: Emaar Development P.J.S.C., Emaar Properties (P.J.S.C), Emaar Dubai South Dwc Llc, Dubai Hills Estate L.L.C, Dubai Creek Harbour L.L.C, Mina Rashid Properties L.L.C, The Lagoons Phase One L.L.C, Dwtc Emaar L.L.C.

Which projects are on Emaar's record?

ProjectAreaUnitsBuiltStartedMilestoneSold, 12 monthsPer sq ftCheck
Greenside ResidenceDubai Hills49093%Nov 2023No date on record52AED 2,287
Fairway Villas 2Madinat Al Mataar17692%Jul 2023Planned Dec 202623Sold as land
Park GateHadaeq Sheikh Mohammed Bin Rashid4790%May 2024No date on record4Sold as land
AeonDubai Creek Harbour26290%May 2024No date on record11AED 2,296
Marina ShoresDubai Marina44487%Dec 2022Planned Dec 202645AED 2,695
Creek Waters 2Dubai Creek Harbour45582%Aug 2023Planned Dec 202750AED 2,339
The Oasis - PalmieraMe'Aisem Second26582%Aug 2023No date on record34Sold as land
The Valley - AlanaAl Yufrah 132282%Nov 2023No date on record17AED 1,138

Questions people ask

Quick answers, from the same deals as the rest of this page.

How many projects has Emaar finished?

175, with 61,837 units.

How long does Emaar take to build?

About 44 months from start to 100%, for the 136 that have finished.

Does Emaar finish on time?

DLD's dates can't tell you, because DLD often replaces the planned date with the finish date once a project is done. Of projects started by 2022, 156 of 170 are finished.

Has Emaar cancelled any projects?

14, on DLD's record: Aviara, Bellaria, Burj Park Iii, Burj Park V, Burj Place, Claren 2, Dubai Marina, Expo Golf Apartments, Grand Boulevard, M Burj, Saffron, Serenia, The Assembly, The Mansion.

Which company is behind Emaar?

DLD lists Emaar Development P.J.S.C. as the developer.

About our data

Where our numbers come from

Project status comes from DLD's project records, read on 5 Nov 2026. Prices come from every sale registered with DLD, to 3 Nov 2026.

What's counted
Projects DLD lists under the 8 companies named in the card "Who is behind Emaar?".
Finishes what it starts
Projects by start year and their DLD status today. A start year counts as old enough once the typical build time has passed. It says nothing about whether dates were met.
Units
DLD's count for each project. It can include shops and offices as well as homes.
Build time
Months from DLD's start date to the first inspection at 100%, for projects that have finished. Projects still running aren't in it.
Typical at the same age
How built the developer's other projects were at the same number of months, finished and still running, using the middle project.
Planned end
DLD's latest date. DLD can rewrite it, and often replaces it with the finish date once a project is done, so we never use it to say a developer finished on time.
Neighbours
Ready sales in the last 12 months in the same area, from other developers. Home types are weighted to match, so a studio-heavy developer isn't compared with family homes.
Rent on ready price
A year of new-lease rent on this developer's buildings, as a share of the typical ready price, before service charges and fees.

We update with every data release. This page was last updated on 3 Nov 2026.