Jag3 handed over · 8 in progress · 4 not started · 0 cancelled

At a glance

Updated with deals to 30 Oct 2026
Finishes what it starts3 of 3projects started by 2022

3 finished.

Due in 2029944units, on DLD's latest dates

0% built today.

Start to 100%44 monthstypical, of the 3 finished

Half took 31 to 47 months.

Sells off-plan forAED 1,565per sq ft, last 12 months

1-bed homes rent for about 7.4% of the ready price.

Jag projects, build times and prices

Does Jag finish what it starts?

3 of 3 projects started by 2022 are finished

None was cancelled. Many projects started since 2023 are still being built, so those years aren't a result yet. This counts projects, and it says nothing about dates.

Old enough to judge

1
17
1
18
19
20
21
1
22

Too recent to judge

23
3
24
5
25
4
26
FinishedBeing builtProjects, by the year they started

What's due, and how built is it?

944 units due in 2029

They're 0% built today. Jag's busiest year so far finished 605 units, in 2022.

Most in one year: 605
  • 2027
    77616% built
  • 2028
    5127% built
  • 2029
    9440% built
  • 2030
    7170% built
  • No date on record
    82119% built
Built so farStill to build

DLD's latest dates, which can move.

Delivery intelligence

Which dates need a closer look?

Active projects past their planned end0 of 9On DLD's latest dates, among projects with a date
Active projects with no planned end3821 units

How does Boulevard Park 2 compare with other Jag projects at the same age?

Boulevard Park 2Typical Jag projectMiddle half of Jag projects

Build intelligence

Is it keeping pace?

DLD shows no building work yet. Its last inspection was on 29 Jun 2026, 2 months in.

  • It started 6 months ago. Other Jag projects were typically 0.5% built by then.
  • DLD's latest planned end is Nov 2029.
  • 314 homes sold in the last 12 months, at about AED 1,698 per sq ft.
See its page →

How far along is what's being built?

Most units are at under 25% built.

Bars show units. Pick a row to list those projects.

How long does Jag take to build?

Finished projects typically took 44 months from start to 100%.

FinishedStill being built, so far

Recent years look quick because only the fastest have finished. Months as DLD records them.

What do Jag homes sell and rent for?

Most rent for the price1-bed homesA year's rent is about 7.4% of the ready price
Homes sold, last 12 months1,1611,107 off-plan, 54 ready
HomeOff-plan nowRent a yearRent on ready price
StudioAED 676kNot knownNot known
1 bedAED 1.41MAED 60k7.4%
2 bedAED 1.95MAED 75k7.0%
3 bedAED 2.98MAED 100k6.5%
4 bedAED 5.67MNot knownNot known

Sold each month

Oct
Nov
Dec
Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct

673 of 1,196 sales in these 13 months registered from Apr 2026 to Jul 2026.

Do Jag homes resell above their neighbours?

Ready Jag homes sold for about 58% more than others nearby, per sq ft, across 45 sales in 1 area.

  • Jabal Ali First
    +58%
JagOthers, same home types

Last 12 months. Pale rows have few sales.

Jag logo

Who is behind Jag?

DLD lists Jag Development L.L.C as the developer, number 1233.

Which projects are on Jag's record?

ProjectAreaUnitsBuiltStartedMilestoneSold, 12 monthsPer sq ftCheck
Hillside Residences 1Jabal Ali First23526%Jan 2024No date on record20AED 1,251
Hillside Residences 2Jabal Ali First28018%Jan 2024No date on record11AED 1,313
South Garden AJabal Ali First26016%Jan 2025Planned Dec 202733AED 1,320
South Garden BJabal Ali First25816%Jan 2025Planned Dec 202729AED 1,357
South Garden CJabal Ali First25816%Jan 2025Planned Dec 202727AED 1,220
Hillside Residences 3Jabal Ali First30613%Jan 2024No date on record25AED 1,410
South Garden EJabal Ali First2568%Oct 2025Planned May 2028223AED 1,420
South Garden DJabal Ali First2566%Oct 2025Planned May 2028216AED 1,485

Questions people ask

Quick answers, from the same deals as the rest of this page.

How many projects has Jag finished?

3, with 908 units.

How long does Jag take to build?

About 44 months from start to 100%, for the 3 that have finished.

Does Jag finish on time?

DLD's dates can't tell you, because DLD often replaces the planned date with the finish date once a project is done. Of projects started by 2022, 3 of 3 are finished.

Has Jag cancelled any projects?

None on DLD's record.

Which company is behind Jag?

DLD lists Jag Development L.L.C as the developer.

About our data

Where our numbers come from

Project status comes from DLD's project records, read on 5 Nov 2026. Prices come from every sale registered with DLD, to 30 Oct 2026.

What's counted
Projects DLD lists under Jag Development L.L.C.
Finishes what it starts
Projects by start year and their DLD status today. A start year counts as old enough once the typical build time has passed. It says nothing about whether dates were met.
Units
DLD's count for each project. It can include shops and offices as well as homes.
Build time
Months from DLD's start date to the first inspection at 100%, for projects that have finished. Projects still running aren't in it.
Typical at the same age
How built the developer's other projects were at the same number of months, finished and still running, using the middle project.
Planned end
DLD's latest date. DLD can rewrite it, and often replaces it with the finish date once a project is done, so we never use it to say a developer finished on time.
Neighbours
Ready sales in the last 12 months in the same area, from other developers. Home types are weighted to match, so a studio-heavy developer isn't compared with family homes.
Rent on ready price
A year of new-lease rent on this developer's buildings, as a share of the typical ready price, before service charges and fees.

We update with every data release. This page was last updated on 30 Oct 2026.