Damac103 handed over · 90 in progress · 3 not started · 32 cancelled

At a glance

Updated with deals to 3 Nov 2026
Finishes what it starts94 of 127projects started by 2021

94 finished, 1 still being built, 32 cancelled in all.

Due in 203010,750units, on DLD's latest dates

0.2% built today.

Start to 100%53 monthstypical, of the 65 finished

Half took 43 to 64 months.

Sells off-plan forAED 1,799per sq ft, last 12 months

3-bed homes rent for about 7.9% of the ready price.

Damac projects, build times and prices

Does Damac finish what it starts?

94 of 127 projects started by 2021 are finished

Aykon City 3 is still being built, 83 months in and 31% built. 32 were cancelled. 125 of the 127 are registered to 9 other companies. They count here. Many projects started since 2022 are still being built, so those years aren't a result yet. This counts projects, and it says nothing about dates.

Old enough to judge

5
06
6
07
19
08
1
09
17
10
4
11
6
12
19
13
33
14
2
15
5
16
5
17
1
18
2
19
20
2
21

Too recent to judge

17
22
13
23
20
24
33
25
18
26
FinishedBeing builtCancelledProjects, by the year they started

What's due, and how built is it?

10,750 units due in 2030

They're 0.2% built today. Damac's busiest year so far finished 3,900 units, in 2018.

Most in one year: 3,900
  • Planned end passed
    4,76785% built
  • 2026
    3649% built
  • 2027
    6,77030% built
  • 2028
    7,85210% built
  • 2029
    9,1417% built
  • 2030
    10,7500.2% built
  • No date on record
    3,93853% built
Built so farStill to build

DLD's latest dates, which can move.

Delivery intelligence

Which dates need a closer look?

Active projects past their planned end10 of 79On DLD's latest dates, among projects with a date
Active projects with no planned end143,938 units

How does Damac Lagoons - Valencia compare with other Damac projects at the same age?

Damac Lagoons - ValenciaTypical Damac projectMiddle half of Damac projects

Build intelligence

Is it keeping pace?

It's behind other Damac projects. It was 5% built at 18 months, when they were typically 20% built.

  • DLD's latest planned end is Feb 2028.
  • Last inspected on 20 May 2026.
  • 1,359 homes sold in the last 12 months, at about AED 1,830 per sq ft.
See its page →

How far along is what's being built?

Most units are at under 25% built.

Bars show units. Pick a row to list those projects.

How long does Damac take to build?

Finished projects typically took 53 months from start to 100%. The 5 started in 2017 took longest, about 75 months.

FinishedStill being built, so far

Recent years look quick because only the fastest have finished. Months as DLD records them.

What do Damac homes sell and rent for?

Most rent for the price3-bed homesA year's rent is about 7.9% of the ready price
Sold as landAED 3.04MTypical, 1,869 sales. DLD gives no home type
HomeOff-plan nowRent a yearRent on ready price
StudioAED 736kAED 42k7.6%
1 bedAED 1.27MAED 70k7.0%
2 bedAED 2.02MAED 100k6.2%
3 bedAED 5.87MAED 210k7.9%
4 bedAED 2.82MNot knownNot known

Sold each month

Oct
Nov
Dec
Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct

Sales were highest in Oct 2025, with 1,691 registered.

Do Damac homes resell above their neighbours?

Ready Damac homes sold for about 23% less than others nearby, per sq ft, across 1,107 sales in 4 areas.

  • Business Bay
    -20%
  • Jumeirah Village Circle
    -35%
  • Dubai Production City
    -29%
  • Dubai South
    -10%
  • Burj Khalifa
    -40%
  • Dubai Marina
    +3%
  • Arjan
    -35%
DamacOthers, same home types

Last 12 months. Pale rows have few sales.

Where does Damac build?

25% of what's being built is in Al Hebiah Fifth.

  • Al Hebiah Fifth13,992
  • Damac Hills11,192
  • Al Yelayiss 110,550
  • Business Bay10,544
  • Dubai Investment Park Second6,379
  • Jumeirah Village Circle2,830
Finished unitsUnits being built
Damac logo

Who is behind Damac?

Damac was founded in 2002 by Hussain Sajwani and is known for branded residences. Damac Lagoons is one of its largest communities. DLD lists 20 companies as the developer of these projects: Damac Crescent Properties, Island Oasis Properties, Damac Development(L L C), Damac Properties Co (L.L.C), Damac Elite Investment Co. L.L.C, Damac Mry Investment L.L.C, Damac Star Properties (L L C), Damac Prime Development L.L.C, Damac World Real Estate L.L.C, Damac Canal One Property Development L.L.C, Damac Crest Development L.L.C, Damac Crown Properties Company Limited, Damac Business Real Estate Co. L.L.C, Damac C S L Investment L.L.C, Damac Canal Two Property Development L.L.C, Damac Gulf Properties (L.L.C), Damac J R Two Investment L.L.C, Damac J W F Investment L.L.C, Damac Mdn Investment L.L.C, Damac P S L Investment L.L.C.

Which projects are on Damac's record?

ProjectAreaUnitsBuiltStartedMilestoneSold, 12 monthsPer sq ftCheck
Damac Lagoons - PortofinoAl Hebiah Fifth86797%Apr 2022Planned Jun 2025139Sold as land
Damac Lagoons - Nice 1Al Hebiah Fifth50994%Feb 2022Planned Jul 202578Sold as land
Damac Lagoons - MarbellaAl Hebiah Fifth60987%Feb 2023Planned Dec 202544Sold as land
Damac Lagoons - Monte CarloAl Hebiah Fifth42486%Feb 2022Planned Dec 202548Sold as land
Damac Lagoons - Nice 2Al Hebiah Fifth43484%Feb 2022Planned Jul 202535Sold as land
Damac Lagoons - MykonosAl Hebiah Fifth57581%Feb 2023Planned Dec 202536Sold as land
Damac Hills - Golf Gate 2Damac Hills46480%Aug 2023No date on record46AED 1,449
Damac Lagoons - IbizaAl Hebiah Fifth82379%Feb 2022Planned Dec 202576Sold as land

Questions people ask

Quick answers, from the same deals as the rest of this page.

How many projects has Damac finished?

103, with 31,956 units.

How long does Damac take to build?

About 53 months from start to 100%, for the 65 that have finished.

Does Damac finish on time?

DLD's dates can't tell you, because DLD often replaces the planned date with the finish date once a project is done. Of projects started by 2021, 94 of 127 are finished.

Has Damac cancelled any projects?

32, on DLD's record: Admiral Bay, Augusta@Akoya By Damac, Business Place & Park Side, Capital Square, Central Square A & B, Charlotte@Akoya By Damac, Fairway Heights - Sunningdale & Wentwoeth (B), Fairway Heights Murfield & Hoylake (A), Flamingo Cove, Flamingo Heights, Green Acres @ Akoya By Damac, Green Court, Heritage Plaza, Heritage Residence, La Residence 3 At The Lotus, La Residence 4 At The Lotus, Legend 1 @ Akoya By Damac, Legend 2 @ Akoya By Damac, Lincoln Park (Austin), Lincoln Park (Manhattan), Madison Residence (Atlantic), Madison Residence(York), North Bay, Palm Spring, Paramount Hotel-Jumeirah Waterfront, Suberbia Dja - C, The Concourse, The Concourse 2, The Range @ Akoya By Damac, Town Central, Trevi@Akoya By Damac, Tuscan Residences 2 - Palimiro.

Which company is behind Damac?

DLD lists Island Oasis Properties as the developer.

About our data

Where our numbers come from

Project status comes from DLD's project records, read on 5 Nov 2026. Prices come from every sale registered with DLD, to 3 Nov 2026.

What's counted
Projects DLD lists under the 20 companies named in the card "Who is behind Damac?".
Finishes what it starts
Projects by start year and their DLD status today. A start year counts as old enough once the typical build time has passed. It says nothing about whether dates were met.
Units
DLD's count for each project. It can include shops and offices as well as homes.
Build time
Months from DLD's start date to the first inspection at 100%, for projects that have finished. Projects still running aren't in it.
Typical at the same age
How built the developer's other projects were at the same number of months, finished and still running, using the middle project.
Planned end
DLD's latest date. DLD can rewrite it, and often replaces it with the finish date once a project is done, so we never use it to say a developer finished on time.
Neighbours
Ready sales in the last 12 months in the same area, from other developers. Home types are weighted to match, so a studio-heavy developer isn't compared with family homes.
Rent on ready price
A year of new-lease rent on this developer's buildings, as a share of the typical ready price, before service charges and fees.

We update with every data release. This page was last updated on 3 Nov 2026.