Binghatti logo

Binghatti43 handed over · 24 in progress · 13 not started · 0 cancelled

At a glance

Updated with deals to 3 Nov 2026
Finishes what it starts43 of 53projects started by 2024

43 finished, 10 still being built.

Due in 202715,562units, on DLD's latest dates

4% built today.

Start to 100%19 monthstypical, of the 42 finished

Half took 16 to 23 months.

Sells off-plan forAED 1,910per sq ft, last 12 months

Studios rent for about 7.4% of the ready price.

Binghatti projects, build times and prices

Does Binghatti finish what it starts?

43 of 53 projects started by 2024 are finished

Burj Binghatti Jacob & Co. Residences is still being built, 49 months in and 52% built. Mercedes-Benz Places | Binghatti is still being built, 35 months in and 65% built. Bugatti Residences By Binghatti is still being built, 44 months in and 66% built. Binghatti Hills is still being built, 31 months in and 90% built. One By Binghatti is still being built, 32 months in and 50% built. Binghatti Starlight is still being built, 27 months in and 63% built. Binghatti Hillviews is still being built, 25 months in and 33% built. Binghatti Elite is still being built, 23 months in and 53% built. Binghatti Skyrise is still being built, 25 months in and 36% built. Binghatti Haven is still being built, 23 months in and 76% built. Many projects started since 2025 are still being built, so those years aren't a result yet. This counts projects, and it says nothing about dates.

Old enough to judge

1
14
1
15
16
2
17
18
3
19
1
20
3
21
11
22
13
23
18
24

Too recent to judge

15
25
12
26
FinishedBeing builtProjects, by the year they started

What's due, and how built is it?

15,562 units due in 2027

They're 4% built today. Binghatti's busiest year so far finished 4,093 units, in 2025.

Most in one year: 4,093
  • Planned end passed
    10,23747% built
  • 2026
    3,91740% built
  • 2027
    15,5624% built
  • 2028
    3,1900% built
  • No date on record
    1,70190% built
Built so farStill to build

DLD's latest dates, which can move.

Delivery intelligence

Which dates need a closer look?

Active projects past their planned end14 of 36On DLD's latest dates, among projects with a date
Active projects with no planned end11,701 units

How does Binghatti Vintage compare with other Binghatti projects at the same age?

Binghatti VintageTypical Binghatti projectMiddle half of Binghatti projects

Build intelligence

Is it keeping pace?

DLD shows no building work yet. Its last inspection was on 23 Sep 2025, at the start.

  • It started 13 months ago.
  • DLD's latest planned end is Mar 2027.
  • 1,526 homes sold in the last 12 months, at about AED 1,860 per sq ft.
See its page →

How far along is what's being built?

2 had no building work at their last inspection, taken around when they started. They started 13 to 13 months ago.

Bars show units. Pick a row to list those projects.

How long does Binghatti take to build?

Finished projects typically took 19 months from start to 100%. The 11 started in 2024 took longest, about 21 months.

FinishedStill being built, so far

Recent years look quick because only the fastest have finished. Months as DLD records them.

What do Binghatti homes sell and rent for?

Most rent for the priceStudiosA year's rent is about 7.4% of the ready price
Homes sold, last 12 months13,87512,445 off-plan, 1,430 ready
HomeOff-plan nowRent a yearRent on ready price
StudioAED 790kAED 50k7.4%
1 bedAED 1.31MAED 70k6.5%
2 bedAED 2.21MAED 115k7.2%
3 bedAED 5.19MAED 110k5.2%
4 bedAED 7.1MNot knownNot known

Sold each month

Oct
Nov
Dec
Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct

8,109 of 15,930 sales in these 13 months registered from Oct 2025 to Jan 2026.

Do Binghatti homes resell above their neighbours?

Ready Binghatti homes sold for about 21% more than others nearby, per sq ft, across 1,160 sales in 1 area.

  • Jumeirah Village Circle
    +21%
  • Business Bay
    +5%
  • Dubai Healthcare City - Phase 2
    -22%
  • Silicon Oasis
    -10%
BinghattiOthers, same home types

Last 12 months. Pale rows have few sales.

Where does Binghatti build?

20% of what's being built is in Business Bay.

  • Jumeirah Village Circle11,416
  • Business Bay7,866
  • Business Park5,395
  • Majan4,569
  • Dubai Science Park3,693
  • Sama Al Jadaf2,304
Finished unitsUnits being built
Binghatti logo

Who is behind Binghatti?

DLD lists Binghatti Developers Fze as the developer, number 1051.

Which projects are on Binghatti's record?

ProjectAreaUnitsBuiltStartedMilestoneSold, 12 monthsPer sq ftCheck
Binghatti HillsDubai Science Park1,70190%Apr 2024No date on record315AED 1,934
Binghatti HillsideDubai Science Park41180%Jan 2025Planned Jun 2026246AED 2,136
Binghatti HavenDubai Sports City50176%Dec 2024Planned Mar 2026197AED 1,488
Binghatti AmberhallJumeirah Village Circle71070%Feb 2025Planned Feb 2026435AED 1,673
Bugatti Residences By BinghattiBusiness Bay18766%Mar 2023Planned Dec 202531AED 6,987
Mercedes-Benz Places | BinghattiBurj Khalifa16365%Dec 2023Planned Dec 202630AED 5,135
Binghatti RubyJumeirah Village Circle62865%Jan 2025Planned Feb 2026186AED 1,967
Binghatti StarlightAl Jadaf51163%Jul 2024Planned Mar 2026176AED 2,062

Questions people ask

Quick answers, from the same deals as the rest of this page.

How many projects has Binghatti finished?

43, with 13,573 units.

How long does Binghatti take to build?

About 19 months from start to 100%, for the 42 that have finished.

Does Binghatti finish on time?

DLD's dates can't tell you, because DLD often replaces the planned date with the finish date once a project is done. Of projects started by 2024, 43 of 53 are finished.

Has Binghatti cancelled any projects?

None on DLD's record.

Which company is behind Binghatti?

DLD lists Binghatti Developers Fze as the developer.

About our data

Where our numbers come from

Project status comes from DLD's project records, read on 5 Nov 2026. Prices come from every sale registered with DLD, to 3 Nov 2026.

What's counted
Projects DLD lists under Binghatti Developers Fze.
Finishes what it starts
Projects by start year and their DLD status today. A start year counts as old enough once the typical build time has passed. It says nothing about whether dates were met.
Units
DLD's count for each project. It can include shops and offices as well as homes.
Build time
Months from DLD's start date to the first inspection at 100%, for projects that have finished. Projects still running aren't in it.
Typical at the same age
How built the developer's other projects were at the same number of months, finished and still running, using the middle project.
Planned end
DLD's latest date. DLD can rewrite it, and often replaces it with the finish date once a project is done, so we never use it to say a developer finished on time.
Neighbours
Ready sales in the last 12 months in the same area, from other developers. Home types are weighted to match, so a studio-heavy developer isn't compared with family homes.
Rent on ready price
A year of new-lease rent on this developer's buildings, as a share of the typical ready price, before service charges and fees.

We update with every data release. This page was last updated on 3 Nov 2026.