Tiger18 handed over · 8 in progress · 0 not started · 0 cancelled
Auresta TowerBeing built, 4%
Sky Gate TowerBeing built, 5%
Ananda ResidencesBeing built, 3%
Tiger Sky TowerBeing built, 10%
Red SquareBeing built, 27%
Neva ResidencesFinished, 100%
Cloud TowerFinished, 100%
Guzel TowersBeing built, 7%
NoblesFinished, 100%
Seslia TowerFinished, 100%
Blue WaveFinished, 100%
Jade TowerBeing built, 11%
Al Jawhara TowerFinished, 100%
The SquareFinished, 100%
The V TowerFinished, 100%
Lake City TowerFinished, 100%
O 2Finished, 100%
Al Manarah TowerFinished, 100%
Elbrus TowerFinished, 100%
Volga TowerBeing built, 51%
Marina PinnacleFinished, 100%
Dana TowerFinished, 100%
Altai TowerFinished, 100%
ReginaFinished, 100%
Lilium TowerFinished, 100%
SamayaFinished, 100%
At a glance
Updated with deals to 3 Nov 2026
Finishes what it starts14 of 14projects started by 2022
14 finished.
Due in 20282,298units, on DLD's latest dates
4% built today.
Start to 100%42 monthstypical, of the 15 finished
Half took 39 to 44 months.
Sells off-plan forAED 1,606per sq ft, last 12 months
2-bed homes rent for about 8.2% of the ready price.
Tiger projects, build times and prices
Does Tiger finish what it starts?
14 of 14 projects started by 2022 are finished
None was cancelled. Many projects started since 2023 are still being built, so those years aren't a result yet. This counts projects, and it says nothing about dates.
Old enough to judge
1
05
06
07
1
08
1
09
10
11
12
13
1
14
15
1
16
3
17
18
2
19
2
20
21
2
22
Too recent to judge
5
23
4
24
3
25
FinishedBeing builtProjects, by the year they started
What's due, and how built is it?
2,298 units due in 2028
They're 4% built today. Tiger's busiest year so far finished 1,563 units, in 2026.
Most in one year: 1,563
2027
9589% built
2028
2,2984% built
No date on record
2,07525% built
Built so farStill to build
DLD's latest dates, which can move.
Delivery intelligence
Which dates need a closer look?
Active projects past their planned end0 of 5On DLD's latest dates, among projects with a date
Active projects with no planned end32,075 units
How does Auresta Tower compare with other Tiger projects at the same age?
Auresta TowerTypical Tiger projectMiddle half of Tiger projects
Build intelligence
Is it keeping pace?
It's behind other Tiger projects. It was 4% built at 17 months, when they were typically 10% built.
DLD's latest planned end is Dec 2028.
Last inspected on 8 Oct 2026.
241 homes sold in the last 12 months, at about AED 1,600 per sq ft.
Quick answers, from the same deals as the rest of this page.
How many projects has Tiger finished?
18, with 6,921 units.
How long does Tiger take to build?
About 42 months from start to 100%, for the 15 that have finished.
Does Tiger finish on time?
DLD's dates can't tell you, because DLD often replaces the planned date with the finish date once a project is done. Of projects started by 2022, 14 of 14 are finished.