Continental6 handed over · 4 in progress · 0 not started · 0 cancelled

At a glance

Updated with deals to 29 Oct 2026
Finishes what it starts3 of 3projects started by 2019

3 finished.

Due in 2026401units, on DLD's latest dates

50% built today.

Start to 100%72 monthstypical, of the 6 finished

Half took 35 to 88 months.

Sells off-plan forAED 1,630per sq ft, last 12 months

1-bed homes rent for about 9.8% of the ready price.

Continental projects, build times and prices

Does Continental finish what it starts?

3 of 3 projects started by 2019 are finished

None was cancelled. Many projects started since 2020 are still being built, so those years aren't a result yet. This counts projects, and it says nothing about dates.

Old enough to judge

1
11
12
13
1
14
15
16
17
1
18
19

Too recent to judge

1
20
21
1
22
2
23
2
24
1
25
FinishedBeing builtProjects, by the year they started

What's due, and how built is it?

401 units due in 2026

They're 50% built today. Continental's busiest year so far finished 1,294 units, in 2026.

Most in one year: 1,294
  • 2026
    40150% built
  • 2027
    37912% built
  • No date on record
    32865% built
Built so farStill to build

DLD's latest dates, which can move.

Delivery intelligence

Which dates need a closer look?

Active projects past their planned end0 of 3On DLD's latest dates, among projects with a date
Active projects with no planned end1328 units

How does Taiyo Residences compare with other Continental projects at the same age?

Taiyo ResidencesTypical Continental projectMiddle half of Continental projects

Build intelligence

Is it keeping pace?

It's behind other Continental projects. It was 12% built at 18 months, when they were typically 20% built.

  • DLD's latest planned end is Dec 2027.
  • Last inspected on 20 Oct 2026.
  • 268 homes sold in the last 12 months, at about AED 1,595 per sq ft.
See its page →

How far along is what's being built?

Most units are at 50% to 75% built.

Bars show units. Pick a row to list those projects.

How long does Continental take to build?

Finished projects typically took 72 months from start to 100%.

FinishedStill being built, so far

Recent years look quick because only the fastest have finished. Months as DLD records them.

What do Continental homes sell and rent for?

Most rent for the price1-bed homesA year's rent is about 9.8% of the ready price
Homes sold, last 12 months603324 off-plan, 279 ready
HomeOff-plan nowRent a yearRent on ready price
StudioAED 669kAED 38k7.5%
1 bedAED 1.03MAED 95k9.8%
2 bedAED 1.4MAED 75k4.3%
3 bedAED 2.5MNot knownNot known

Sold each month

Oct
Nov
Dec
Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct

356 of 691 sales in these 13 months registered from Nov 2025 to Feb 2026.

Do Continental homes resell above their neighbours?

Ready Continental homes sold for about the same as others nearby, per sq ft, across 34 sales in 1 area.

  • Dubai Marina
    +0%
ContinentalOthers, same home types

Last 12 months. Pale rows have few sales.

Where does Continental build?

40% of what's being built is in Jaddaf Waterfront.

  • Rukan1,139
  • Wadi Al Safa 7774
  • Jaddaf Waterfront447
  • Dubai Marina429
  • Jabal Ali First379
  • Dubai Maritime City282
Finished unitsUnits being built
Continental logo

Who is behind Continental?

DLD lists Continental Investments Lmd L.L.C as the developer, number 958.

Which projects are on Continental's record?

ProjectAreaUnitsBuiltStartedMilestoneSold, 12 monthsPer sq ftCheck
Boutique 23Jaddaf Waterfront32865%Nov 2023No date on record15AED 1,831
La BoutiqueJaddaf Waterfront11953%Jul 2024Planned Dec 20268AED 1,678
The PierDubai Maritime City28248%Jul 2024Planned Dec 202628AED 2,622
Taiyo ResidencesJabal Ali First37912%May 2025Planned Dec 2027268AED 1,595

Questions people ask

Quick answers, from the same deals as the rest of this page.

How many projects has Continental finished?

6, with 2,342 units.

How long does Continental take to build?

About 72 months from start to 100%, for the 6 that have finished.

Does Continental finish on time?

DLD's dates can't tell you, because DLD often replaces the planned date with the finish date once a project is done. Of projects started by 2019, 3 of 3 are finished.

Has Continental cancelled any projects?

None on DLD's record.

Which company is behind Continental?

DLD lists Continental Investments Lmd L.L.C as the developer.

About our data

Where our numbers come from

Project status comes from DLD's project records, read on 5 Nov 2026. Prices come from every sale registered with DLD, to 29 Oct 2026.

What's counted
Projects DLD lists under Continental Investments Lmd L.L.C.
Finishes what it starts
Projects by start year and their DLD status today. A start year counts as old enough once the typical build time has passed. It says nothing about whether dates were met.
Units
DLD's count for each project. It can include shops and offices as well as homes.
Build time
Months from DLD's start date to the first inspection at 100%, for projects that have finished. Projects still running aren't in it.
Typical at the same age
How built the developer's other projects were at the same number of months, finished and still running, using the middle project.
Planned end
DLD's latest date. DLD can rewrite it, and often replaces it with the finish date once a project is done, so we never use it to say a developer finished on time.
Neighbours
Ready sales in the last 12 months in the same area, from other developers. Home types are weighted to match, so a studio-heavy developer isn't compared with family homes.
Rent on ready price
A year of new-lease rent on this developer's buildings, as a share of the typical ready price, before service charges and fees.

We update with every data release. This page was last updated on 29 Oct 2026.